CMEC commissions 810 MWs PTPL power plant

The China Machinery Engineering Corp. (CMEC) successfully commissioned two gas turbines (405 MWs each) for the Punjab Thermal Power Ltd. (PTPL) power plant in the Jhang district. Work on the 443 MWs steam turbine is also underway at a fast pace to achieve the combined-cycle commercial operations, it added. CMEC executed the project as the EPC (Engineering, Procurement, and Construction) contractor.

PTPL has also signed an agreement with CMEC for operating the two gas turbines until the steam turbine is put into commercial operations, after which the two parties will renew the agreement to include the combined-cycle operations as well, an official of the CMEC said.

Work on the steam unit is almost complete but will take around six more months in achieving commercial operations due to complicated pre-commissioning procedures including chemical cleaning of the boiler, the official said.

The plant has a total combined-cycle capacity of 1242 MWs, the report added.

Previous articleQatarEnergy awards McDermott FEED contract
Next articleHeliogen signs LOI with Dimensional Energy
Heat Exchanger World Publisher
Heat Exchanger World is a leading international magazine covering all aspects of the product supply chain of heat exchangers. Heat Exchanger World is part of the KCI Group of Companies. We are a leading knowledge, communication and information company connecting business-to-business professionals by building and sustaining global communities, solving their information needs and helping them to develop their professional life and friendships.