JSC starts Heat Treatment of Steam of “ROOPPUR” NPP-1

The Branch of JSC “AEM-technology” “Atommash” in Volgodonsk (a part of machine-building subdivision of ROSATOM – “Atomenergomash”) has started the Heat Treatment of Steam Generator Vessel for Unit No. 1 of “Rooppur” NPP.

The Item, which has the weight of approximately 160 tons has been placed to the furnace. The temperature of the furnace heating is 650 degrees. The Vessel will be inside for 8 10 h.

Previously, the Steam Generator Vessel was assembled from four Shells and welded them together. During the welding process, about 580 kg of flux and more than 3,000 meters of wire were used.

The Steam Generator is heat exchange equipment, it is a part of the Reactor Plant and it belongs to the 1st safety class equipment. Diameter is more than 4 m, the length of equipment is approximately 15 meters, weight is 340 tons. The set of equipment of one NPP Unit includes four Steam Generators.

Currently, seven Steam Generator Vessels for two Units for “Rooppur” NPP are at different production stages at Atommash.

Previous articleSandia analysis evaluating water saving technologies
Next articleVitherm secures an order for a refinery in China
Heat Exchanger World Publisher
Heat Exchanger World is a leading international magazine covering all aspects of the product supply chain of heat exchangers. Heat Exchanger World is part of the KCI Group of Companies. We are a leading knowledge, communication and information company connecting business-to-business professionals by building and sustaining global communities, solving their information needs and helping them to develop their professional life and friendships.